April 2017 Site Development Update
Site Progress Following positive progress from the main contractor the National Centre will be open for business on the 8th of May (as opposed to the 1st as previously advertised) This slight delay is to…
Site Progress Following positive progress from the main contractor the National Centre will be open for business on the 8th of May (as opposed to the 1st as previously advertised) This slight delay is to…
Saturday the 25th of March saw members of the Northampton MAC arrive at BMFA Buckminster for a pre opening PR day. 32 Members arrived by coach and spent the morning learning about the National Centre…
March 2017 Work on site has continued to progress in line with the schedules set out in the initial programme of works which completes the contractors phase 1 works on or around the 28th of…
February 2017 Work on site has continued to progress well and largely in accordance with the schedules set out in the initial programme of works. Weather of course plays a part and to date three…
January 2017 Work really kicked into gear on site during the second week of January (after the traditional construction industry long Christmas break) The Principal Contractor (Front Row Construction) moved machinery on to site, initially…
December 2016 Work has commenced in earnest and December has been a busy month at Buckminster. We have made the most of a relatively dry month and completed the majority of the works to the…
November 2016 Much has been happening over the previous months but the signing of the lease sets the scene for the ‘serious work’ to commence in accordance with the initial project plan. Lease document signed…
Buckminster Blog Now that the National Centre project is actually happening there is of course lots going on. The aim is to keep a running blog of activity as a way of keeping members up…